ENGINEERING.com has updated it's forum.  To post a question please visit the new Ask@ Forum.   

With a database of over 10000 questions the library will remain available for an extended period.

Q&A


brembo
why the scaffolding need to be inspected within the proceding 7 days and after adverse weather conditions? View All
give me 5 reasons with the explanation

15 years ago - 3 weeks left to answer. - 1 response - Report Abuse
Respond to question
    0      [lnkReport]        0       0       
Share |
  Responses


Niel
Fit:

Engineering.com will no provide you with answer to homework questions but we will give you guidance so you can get the answers to your home work questions.

The basic reason for inspection after an adverse weather event would be safety. Can you think of various safety issues that may occur to scaffolding after an adverse weather event?

Although you are in Malaysia the US OSHA is a good source for safety related information on scaffolding. Below is a link to information on scaffolding inspection rules in the USA.

Niel


15 years ago

Source: http://www.osha.gov/pls/oshaweb/searchresults.category?p_text=scaffolding%20inspection&p_title=&p_status=CURRENT


  0     0         

ENGINEERING.com does not provide engineering advice. The Ask@ service is a forum for members to exchange ideas relating to the world of engineering. We caution users not to accept any responses that they receive without further validation, and not to rely on any engineering advice that they may get from other members of the Ask@ forum. ENGINEERING.com specifically disclaims any obligation to validate or verify any information posted within the Ask@ service. ENGINEERING.com encourages users to seek the services of a professional engineer for any engineering advice they may require.